A leading global operator set out to deliver a mission-critical data center on an accelerated timeline. With thousands of interdependent activities and strict operational deadlines, the project team knew that even minor errors could cascade into costly rework, schedule extensions, and lost revenue.
To bring greater transparency, precision, and control to one of its most complex projects, the operator partnered with XYZ Reality - and within just six weeks, the results spoke for themselves.
Within just six weeks, the impact was clear: 48 critical days saved, a 10-week delay prevented, and £457,000 in error and rework savings.
The value proved so immediate that before this project even closed, the client expanded XYZ Reality’s platform across five additional builds, having seen measurable results and a clear return in weeks, not months.