XYZ Reality Client Success Story

SUBSTRUCTURE CONCRETE WORKS

XYZ Reality Client Success Story

SUBSTRUCTURE CONCRETE WORKS

For structural concrete, any error outside of construction tolerances requires an engineering redesign and often involves costly and timely remedial works.

REWORK SAVINGS

TIME &
MATERIAL

€10K

Excavation; breaking concrete; rebuilding structure

TIME
SAVED

3 WEEKS

Early detection prior to ground infill & structural steel installation

OTHER
COSTS

€100K

Programme delays from structural steel installation

Client Satisfaction:
“In a variable industry like construction, we always find something out of tolerance. It is important to catch these issues in advance to be fit to implement the fix prior to the next trade coming in.” - Construction Manager

The Project

Location:
Denmark
Industry:
Data Centre
Size:
40MW
Project Value:
€300m
Package Value:
€50m
Project Stage:
Concrete Foundations

Problem

For structural concrete, any error outside of construction tolerances requires an engineering redesign and often involves costly and timely remedial works:

  • Breaking, cutting, drilling concrete
  • Reordering structural reinforcement and concrete
  • Recasting the concrete and allowing for curing times

Concrete Substructure - Image 1a


Scope of Works

The Main Contractor partnered with XYZ Reality prior to breaking ground, for the construction of their concrete foundations to ensure that they are built correctly (+/- 5mm) and ready for the structural steel columns:

  • Incorporating HoloSite into the project’s Inspection, Testing and Planning process
  • Inspecting the structures at the lowest value stage - during the setting-out and during the installation of the reinforcement, embedded elements (including holding-down bolts) and formwork

Results

In all areas where HoloSite was deployed, any errors or issues were detected prior to the concrete pour and the concrete foundations were installed within tolerances and without defects.

For the one location where HoloSite could not be deployed, the concrete foundation was built 500mm out of tolerance.

However, using HoloSite’s real-time validation, this issue was raised immediately and prior to any ground infill and the steel column installation

 

Concrete Substructure - Image 4a Concrete Substructure - Image 5a